by Admin | Dec 13, 2015 | Construction History
The construction of the 1st floor is completed. read...
by Admin | Oct 8, 2015 | Construction History
The construction team still preparing the formwork for the 1st floor slab. Estimate concrete pouring will be in early November. read...
by Admin | Sep 3, 2015 | Construction History
Constructing the ground floor read...
by Admin | Jul 28, 2015 | Construction History
Ground Beam Construction in Progress read...
by Admin | Jul 1, 2015 | Construction History
Pile-caps and stump columns construction completed read...
by Admin | May 7, 2015 | Construction History
Piling for the Kindergarten and Primary school building completed. read...